Contractors have driven nearly all the 710 concrete columns to support U.S. 64 bridge connecting Outer Banks with rest of North Carolina.
COLUMBIA, N.C. (WNCT) — The construction to replace the Lindsay C. Warren (Alligator River) Bridge on U.S. 64 has progressed to 30% after almost one year. The North Carolina Department of ...
Just 11 months into the three and a half year project, 682 of the 710 pilings have been driven into the ground for the brand new bridge DARE COUNTY, N.C. — Nearly a year ago, construction began to ...
TYRRELL COUNTY, N.C. (WITN) - A new bridge over Alligator River is taking shape as construction crews have completed about 95% of foundation work since construction began in February 2025. The Lindsay ...
Add Yahoo as a preferred source to see more of our stories on Google. Workers will soon drive the last of hundreds of concrete columns into the bottom of the Alligator River that will hold up a new ...
Skanska finished 682 of 710 foundation piles. Final piles will be in place this month. New 3.2-mile bridge rises to 65 feet, widens lanes and adds 8-foot shoulders. Project uses precast concrete, GPS ...